Sidewalk Replacement - Orient Way

Please be advised that sidewalk replacement occurring on Orient Way from Glen Road to Passaic Avenue is scheduled to occur as follows for the remainder of the week. The borough recognizes that this work has created inconveniences and has confirmed engineering staff will be onsite to respond to resident’s concerns. Please check the website for updates or changes to the schedule depending on weather conditions.

April 18th
Pour Orient Way - west side
Demo Orient Way - east side

April 19th
Form Orient Way - east side
Pour Orient Way - east side

April 20th
Final pours and finish brickwork
Clean up and driveway restoration

April 21st
Additional repairs and restoration work as needed